Liège Airport: Over 13,000 m² of runway renovated in 12 hours

A major technical and logistical operation restored the main runway in a single day, mobilizing nearly 120 people.

Aéroport de Liège : plus de 13 000 m² de piste rénovés en 12 heures

Société wallonne des aéroports

The main runway at Liège Airport underwent an intensive 13,000 m² renovation in just 12 hours on November 10, 2026. The operation, managed by SOWAER, mobilized nearly 120 people and considerable material resources.

A large-scale intervention took place on November 6 on the main runway of Liège Airport, between taxiways Sierra 2 and Sierra 3. The objective was to renovate over 13,000 m² of aeronautical pavement and make the infrastructure fully operational in just 12 hours.
The construction site, which ran from 10 a.m. to 10 p.m., followed a tight schedule including milling the old surface, laying new asphalt, drying, repainting markings, and restoring the lighting system. In total, 13,000 m² of pavement were restored over an area approximately 870 meters long and 16 meters wide.
To accomplish this project, nearly 120 people were mobilized, along with 35 trucks in continuous rotation, 4 large milling machines, 4 pavers, and up to 16 compacting rollers, supplemented by other specialized equipment.
The work was carried out by COLAS and its subcontractors (Theis Marcel, Ets Lambert Marquage, and JDC Airports), under the coordination of Benjamin Liégeois and Marc-Olivier Blezer for SOWAER. The success relied on close coordination between the various trades and services, including site access, safety, security, and the restoration of the lighting system.
SOWAER thanked the teams and partners, including Liege Airport, Liège Airport-Security, the Service public de Wallonie, and Protection UNIT, for their involvement. This operation also enhanced SOWAER's expertise for future airport infrastructure maintenance and development projects.
Based on information from the official source: SOWAER — Société wallonne des aéroports (10/11/2026)